The preliminary design phase of the project is currently underway and being performed by the County’s Engineer. The following overall project milestones have been established:

Design
May 2016-November 2017

GMP Development and Project Procurement
October 2017-December 2017

NTP
February 2018

Substantial Completion
April 2021

Final Completion
October 2021